NHPC, a state-owned company, said an NHPC settlement with M/s Patel-L&T Consortium covers claims tied to Parbati-III HE Project (Ref. II). Payment was made on 17.11.2026 after the matter went before the Conciliation Committee of Independent Experts (CCIE-III) in conciliation
PSU, energy, business and infrastructure coverage
NHPC settlement sets revised contractor payment
₹256.10 Crore was PLNT’s earlier demand, while the settlement came to ₹42.62 Crore. The claim concerned delays in handing over the site and adverse geological conditions. NHPC and PLNT withdrew their respective claims under the agreement.